Overview
CIR worked with Hohl Industrial Services, providing the electrical work necessary to build a waste water treatment plant in skids.
Project Details
Timeline: March 2006 - November 2006
Customer: Veolia Water
General Contractor: Hohl Industrial Services
Project Manager: Greg Jakubowski
Location: Built in Tonawanda, NY, shipped to Iceland
Customer: Veolia Water
General Contractor: Hohl Industrial Services
Project Manager: Greg Jakubowski
Location: Built in Tonawanda, NY, shipped to Iceland
Category
Industrial
Overview of Job
CIR worked with Hohl Industrial Services, providing the electrical work necessary to build a waste water treatment plant in skids, or 15 by 30 meter sections. Each of the 12 skids was assembled one at a time at Hohl's River Road location and shipped from Tonawanda to Iceland for final assembly. Once all 12 skids were completed and shipped, CIR Foreman Earl Kirbis supervised the electrical portion of the final assembly on-site at the Fjardall Aluminum Plant in Iceland.